Rāwhiti School
Reflecting the shift toward flexible, future-focused learning environments

Sector: Education
Location: Christchurch, New Zealand
Architect: TOA Architects
Builder/Main Contractor: Armitage Williams Construction
Installer: Wayman Roofing Services Limited
Products: KSN1000FC Five Crown Roof & Wall Panel
Rāwhiti School is a purpose-built primary school in North New Brighton, Christchurch, delivered as part of the wider Christchurch schools rebuild programme following the Canterbury earthquakes.
Opened in 2016, the project brought together three school communities into a single contemporary campus, The school’s design responds to contemporary pedagogy, with flexible learning spaces that support collaboration, independent learning and a variety of teaching styles and long-term community resilience. This school accommodates up to 600 students and reflects the shift toward flexible, future-focused learning environments.
The school is defined by a single-storey, low-lying built form stretched across a large coastal site, a response shaped by the local environment. The elongated layout creates shelter from prevailing winds while establishing a strong relationship between indoor teaching spaces and generous outdoor learning areas. Set back from the road, the buildings help frame a substantial outdoor environment that includes playgrounds, an amphitheatre, artificial turf, bike and scooter tracks, gardens and pool facilities. Rather than treating these as secondary amenities, these are an extension of the learning environment, reinforcing the school’s emphasis on movement, wellbeing and engaging education.
The design includes 6 studios which all operate as flexible learning spaces, breakout rooms, a library, multi-purpose hall, administration areas and resource spaces, all planned to support collaborative teaching models and varied styles of learning. Materially and visually, the architecture draws on subdued tones and local references, with the school’s name and identity thoughtfully expressed throughout.
In 2025 the original roof needed replacing, but the replacement of the existing school roof presented a complex construction challenge, with the works required to be carefully planned and sequenced around the operation of a functioning school. Four key considerations shaped the delivery strategy: time, procurement, site access, and material disposal.


Time & Construction Sequencing
The overarching objective was to complete most of the roofing works during the 2025/26 Christmas school holiday period, minimising disruption to students, staff and the day-to-day operation of the school.
This required close coordination between the school staff, Armitage Williams Construction, Wayman Roofing Services, and Kingspan to secure labour and materials during a period that coincides with the traditional industry shutdown. A further challenge was the uncertainty surrounding the removal of the existing roof. Until the works commenced, the condition and construction of the existing roof meant that the rate of removal - and therefore the achievable daily production - could not be accurately established.
In response, the construction programme was developed around a staged approach. In consultation with Armitage Williams Construction and the school, it was agreed that the primary 4,300 m² of roofing over the learning spaces, administration areas and library would be completed during the Christmas closure, with the remaining 480 m² over the gymnasium scheduled for the first-term holidays in 2026. This approach provided greater certainty around the school's reopening while allowing the construction team to respond to conditions encountered during the works.
Site access was provided on the afternoon of 17 December, with the school requiring the site to be fully handed back by 29 January. The compressed programme therefore required a high level of coordination and daily planning across all trades.
Procurement & Just-in-Time Delivery
Material procurement was critical to achieving the programme. The new roof utilised a locally manufactured Kingspan roofing system, KSN1000FC Five Crown Roof & Wall Panel allowing for a just-in-time production and delivery strategy. The full 4,300 m² required for the primary stage was manufactured and delivered over two consecutive days, 18 and 19 December. This sequencing avoided the need for extensive on-site storage and allowed material deliveries to align directly with the establishment of the work areas.
At the same time, Scaffold Systems Canterbury commenced scaffold installation while the Wayman Roofing Services team began removing existing spouting, flashings and other fixtures required to prepare the roof for replacement. Coordinating these activities concurrently allowed the project to move rapidly from site establishment into the main roofing works.


Access & Site Logistics
Unlike a conventional construction site, the school was an established operational environment with existing fencing, landscaping, buildings, pedestrian routes and other site constraints. Maintaining these features while safely moving large quantities of new and removed roofing material presented a significant logistical challenge.
A key part of the construction planning was determining how new roofing panels could be efficiently transferred from delivery vehicles to the individual work faces, while simultaneously removing the existing roofing from the building.
The project team worked closely with Titan Cranes to develop a lifting strategy that enabled the new roofing panels to be safely and efficiently placed within the school grounds. Wayman Roofing Service's extensive experience with Kingspan systems further supported this process, allowing the team to commence installation as soon as materials arrived at site. This coordinated approach to lifting and material movement was critical to maintaining productivity within the restricted site environment and protecting the surrounding school infrastructure.
Removal & Material Disposal
The removal of the existing roofing presented a second logistical challenge. Large volumes of roofing material needed to be safely removed from the building, temporarily stored and then taken off site without compromising the school's wider operations. The school supported the construction process by making a portion of the car park available for temporary storage of the removed material. This provided the project team with a controlled area to accumulate material while coordinating its removal.
Prior to construction commencing, the existing roofing product was also advertised for reuse. Rather than treating all the removed material as waste, arrangements were made with individuals and local community groups to collect suitable material directly from site. In many cases, material was made available at no cost where recipients could arrange prompt collection. This approach reduced the volume of material requiring conventional disposal while extending the useful life of the existing roofing materials and providing a practical benefit to the local community.

Together, the programme strategy, just-in-time supply, coordinated site logistics and approach to material reuse enabled the roof replacement to be delivered within a highly constrained operational environment, maintaining the primary objective of minimising disruption to the school, the outcome is a high performing warm roof that will stand up to the element for many years to come.
School roofs have a tendency of becoming the long-term storage area for a plethora of sports equipment. This was certainly the case when the Wayman Roofing Services team got up on the old roof to start removing it, shoes, hats, balls and more were found. This sparked an idea to leave the school a departing gift at the end of the project. While a new high-performance roof is an exceptional improvement for the school, collectively Armitage Williams Construction, Wayman Roofing Services and Kingspan have donated $1500 to Rawhiti School for new sports equipment for the kids to enjoy.
Performance on Display.





Download or share the PDF of this case study
Find out more about the product mentioned in this project.

KSN1000FC Five Crown Roof & Wall Panel
NZ-made trapezoidal panel with a high performance PIR insulated core